The Utility Plan Layout map below provides an overview plan of the public construction for sewer and water mains.  The map is a DRAFT and will be updated throughout the design and construction phases. Click to expand the picture.







Racine Water Utility

The Racine Water Utility Project Bidding Process follows Wisconsin State Statutes and is as follows:

  • Design complete and first advertisement to paper (7 days before first advertisement) appears.

  • Second advertisement (7 days after first advertisement).

  • Open bids (7 days after second advertisement).

  • Award of Bids (Last Tuesday of the month at Water Commission meeting).

  • Execute construction contract (about 30 days after notice of award).

  • Earliest construction start (7 days after contracts are executed).